We are having a problem understanding ATP and Supplier Lead Time versus Procurement Lead Time in SAP by Design. For Example, if we have a Supplier Lead time of 15 days and a Procurement Lead time of 45 days (due to transit) 1-which lead time does the system using to confirm availability(ATP)? How are the fields supposed to work? 2-Are there different situations in which the system would use one date in one scenario and one date in another? We have seen the system use both dates (It used 15 days for confirmed availability on one order and then used 45 days for the other order) and we are not able to determine why, because we could find no difference between the 2 parts/orders. Any help anyone could provide would be greatly appreciated! Thanks
↧